Freestanding, Field-Installed Starter
Assemble and install compressor terminal box in desired orientation, and cut necessary
conduit openings in conduit support plates. See Figure 25 and Figure 27. Attach power leads to
compressor terminals in accordance with job wiring drawings, observing caution label in
terminal box. Use only copper conductors. The motor must be grounded in accordance with
NEC (National Electrical Code), applicable local codes, and job wiring diagrams. Installer is
responsible for any damage caused by improper wiring between starter and compressor motor.
IMPORTANT: Be sure to ground the power circuit in accordance with the National
Electrical Code (NEC), applicable local codes, and job wiring diagrams. Also, make
sure correct phasing is observed for proper rotation.
Click here for Figure 24 — 19XL with Optional Unit-Mounted Starter
IMPORTANT: Do not insulate terminals until wiring arrangement has been checked and
approved by Carrier start-up personnel. Also, make sure correct phasing is followed
for proper motor rotation.