Step 2 Install Control Wiring (See Fig. 14-17)
38AKS028-044
1. Install a field-supplied relay with a 24-v coil
(HN61KK324 suggested) and normally closed contacts
rated for 20 va at 125 vac inductive load. Mount this relay
near the control relay (CR1) in the 38AKS control box.
NOTE: This relay is identified in Fig. 14 as HGR (hot gas
relay).
2. COIL WIRING
Connect a field-supplied wire between TB3-3 and
HGR-1 (L1 side of coil). Connect a field-supplied wire
between TB3-7 and HGR-3 (L2 side of coil).
3. SOLENOID WIRING
a. Add a field-supplied wire between TB2-2 and
HGR-5.
b. Connect one leg of the hot gas bypass solenoid to
HGR-6.
c. Connect the other wire from the hot gas bypass
solenoid to terminal TB2-3.
38AH024-034
1. Install a field-supplied relay with a 115-v coil
(HN61KJ510 suggested) and normally closed contacts
rated for 20 va at 125 vac inductive load. Mount this relay
near the control relay (CR1) in the 38AH control box.
NOTE: This relay is identified in Fig. 15 as HGR (hot gas
relay).
2. COIL WIRING
Connect a field-supplied wire between TB3-3 and
HGR-1 (L1 side of coil). Connect a field-supplied wire
between TB3-1 and HGR-3 (L2 side of coil).
3. SOLENOID WIRING
a. Add a field-supplied wire between TB3-2 and
HGR-4.
b. Connect one leg of the hot gas bypass solenoid to
HGR-5.
c. Connect the other wire from the hot gas bypass
solenoid to terminal TB3-1.
38AH044-084 SINGLE CIRCUIT APPLICATIONS
1. Install a field-supplied relay with a 115-v coil
(HN61KJ510 suggested) and normally closed contacts
rated for 20 va at 125 vac inductive load. Mount this relay
near the control relay (CR1) in the 38AH control box.
NOTE: This relay is identified in Fig. 16 as HGR (hot gas
relay).
2. COIL WIRING
Connect a field-supplied wire between TB3-3 and
HGR-1 (L1 side of coil). Connect a field-supplied wire
between TB3-7 and HGR-3 (L2 side of coil).
3. SOLENOID WIRING
a. Add a field-supplied wire between TB3-5 and
HGR-4.
b. Connect one leg of the hot gas bypass solenoid to
HGR-5.
c. Connect the other wire from the hot gas bypass
solenoid to terminal TB3-7.
38AH044-104 DUAL CIRCUIT APPLICATIONS
1. Install a field-supplied relay with a 115-v coil
(HN61KJ510 suggested) and normally closed contacts
rated for 20 va at 125 vac inductive load. Mount this relay
near the control relay (CR1) in the 38AH control box.
LEGEND
*Pilot valve connects directly to bypass valve per sketch A.
Fig. 13 Hot Gas Bypass Piping
TXV
Thermostatic Expansion Valve