Connect Piping
Install Water Piping to Heat Exchangers
Install piping using job data, piping drawings, and procedures outlined below. A typical piping
installation is shown in Figure 15.
Click here for Figure 13 — 19XL Accessory Spring Isolation (Shown with Accessory
Soleplates)
Click here for Figure 14 — Typical 19XL Low Profile Isolation Assembly
CAUTION
CAUTION
!
Factory-supplied insulation is not flammable but can be damaged by welding
sparks and open flame. Protect insulation with a wet canvas cover.